Continued transport of the pumping housing
· 07 Apr · 2022
After a brief stopover in St. Pölten, our journey with the pumping housing from Italy continued to the power plant Gerlos in Zillertal.
As at the last stages several obstacles have had to be removed. Because of an avenue of trees the load had to be turned up on the final metres. The good then was 7,70m high.
The transportation measures were:
30,00m x 6,50m x 4,50m x 115to
The turned up transportation was:
21,00m x 4,10m x 7,70m x 115to