110-ton transformers Maishofen - Uttendorf
· 04 Nov · 2024
Transport of two 110-ton transformers
In October/November, we transported two 110-ton transformers for our client from Maishofen railway station to the Uttendorf power plant and then onward to the Tauernmoos power plant. 🚚
The two transformers arrived by rail at Maishofen station 🛤 🚉, where they were each unloaded using two 220-ton telescopic cranes 🪝 onto our road low-loader and, under bright sunshine, transported to the ÖBB power plant in Uttendorf 🚛.
At Uttendorf, the transformers were transferred onto self-propelled modular transporters and hauled up the mountain to the new Tauernmoos power plant site 🏔.
Dimensions of the two road transports:
Length: 32.50 m / Width: 3.20 m / Height: 4.60 m / Weight: 166 tons 🏋
We would like to thank our client for this great assignment and all those involved for their outstanding work! 👷♂💪🤩