Wiestal power plant

· 30 Apr · 2024

With our 70-ton telescopic crane, we lifted the roof of the gauge house, the sluice gates, and the framework for our client so that all components could be overhauled. 

Since the crane had to be set up directly on the single-lane connecting bridge from the old Wiestal road to the Wiestal state road — and the bridge therefore had to be closed — an application for approval had to be submitted in good time to the responsible authority.

We were pleased to handle this approval process as well as the provision of the necessary signs and barriers for the bridge closure on behalf of our client.

Illustration Name
Illustration Name
Peace Zeichen

We Want You!

Vacancies at Knoll Logistik

We are always looking for experienced and reliable staff to grow our team.
The following positions are currently available